During the past weeks of March 18 & 25, we accomplished the following work:

  • Illumination work, including light bases, cables, and poles, continued along Route 8 SB Exits 13 to 12.
  • Pipe lining work continued (see photos below) throughout the Project limits on Route 8 NB and SB and on local roads.

For the weeks of April 1 & 8, we will continue:

Day Shift:

    • Illumination work on light bases, cables, and poles along Route 8 SB Exit 13 to 12.

Night Shift:

    • Lining of pipes throughout the Project limits from Exits 15 to 22, both NB and SB and on local roads.
    • Pothole repair work across Route 8 NB and SB spanning from Exits 15 to 22, as necessary.

Next Post
Update for the Weeks of April 22 & 29, 2024
Previous Post
Update for the Weeks of March 18 & 25, 2024