During the past weeks of March 4 & 11, we accomplished the following work:

  • Illumination work, including light bases, cables, and poles, continued along Route 8 SB Exits 14 to 13.
  • Pipe lining work continued throughout the Project limits on Route 8 NB and SB and on local roads.

For the weeks of March 18 & 25, we will continue:

Day Shift:

  • Illumination work on light bases, cables, and poles along Route 8 SB Exit 15 to 13, and on local roads.
  • Pothole repair work across Route 8 NB and SB spanning from Exits 15 to 22, as necessary.

Night Shift:

  • Lining of pipes throughout the Project limits from Exits 15 to 22, both NB and SB and on local roads.