Project Plans

  1. Home
  2. Project Plans

Project Schedule

  • June 10, 2022 – Notice to Proceed
  • Fall & Winter 2022 – Site Investigations
  • February 2023 – Final Design Submittal
  • Spring 2023 – Anticipated Design Release for Construction
  • Spring 2023 – Anticipated Construction Start
  • December 2024 – Project Completion

Current Project Status

  • Completing investigations and cleaning
  • Final Design is underway
  • Permit is underway

Construction Activities

  • Work will be completed by taking lanes during off-peak hours
  • Mostly night work with some daytime activities
  • Ramp closures and detours at night
    • Anticipated two to three nights per ramp
    • Local road detours will be coordinated with Towns (detour agreements)
    • Announcements will be found on the website

Construction Staging & Phasing

  • Stage 1 – Shoulder rehabilitation
  • Stage 2 – Median Reconstruction
  • Stage 3 – Mainline pavement reconstruction
  • Work progression South to North
  • Center median reconstruction  – one-mile increments
  • Concrete pavement base repairs begin when center median work has progressed three miles