During the past weeks of April 1, 8, & 15, we accomplished the following work:

  • Illumination work, including light bases, cables, and poles, continued along Route 8 SB Exits 13 to 12.
  • Pipe lining work continued throughout the Project limits on Route 8 NB and SB and on local roads.

For the weeks of April 22 & 29, we will continue:

Day Shift:

  • Illumination work on light poles and cables along Route 8 SB Exit 15 to 12.
  • Lining of pipes throughout the Project limits from Exits 15 to 22, both NB and SB and on local roads.
  • Cleaning of pipes throughout the Project limits from Exits 15 to 22, both NB and SB and on local roads.
  • Pothole repair work across Route 8 NB and SB spanning from Exits 15 to 22, as necessary.

Upcoming Night Work Beginning May 6:

  • Night work milling and paving will begin on May 6th throughout the entire project limits from Exit 15 to 22 both Northbound and Southbound.
  • Signage will be posted on the jobsite.