This past week of April 17, we continued to:

  • Perform drainage site investigations between Exits 15 and 22
  • Perform work on Route 8, both northbound and southbound
  • Implement temporary traffic patterns

During the weeks of April 24 – May 1, upcoming work is anticipated to be as follows:

  • Drainage site investigation with anticipated completion by May 1
  • Highway Illumination and Incident Management System (IMS) work anticipated to begin on May 1
  • Illumination and IMS work will begin at Exit 17 and will commence southbound along the Route 8 corridor
  • Work will take place during the daytime, with intermittent lane closures

Northern limit of the project (exit 22), looking south

Above: Northern limit of the project (Exit 22), looking south

Next Post
Update: Week of May 8, 2023
Previous Post
Update: Week of April 10, 2023