This past week of May 15, the following work took place:

  • Drainage site investigations were completed
  • Highway Illumination and Incident Management System (IMS) work continued

During the weeks of May 22 – May 29, upcoming work is as follows:

  • Illumination and IMS work will continue Mondays through Thursdays, northbound along Route 8
  • This work consists of trenching and backfilling, installing light pole foundations, and installing cable between the foundations

DID YOU KNOW? CTDOT launched a Speed Safety Camera Program along the Route 8 corridor. Learn more here and Know the Zone!

Electrical trenching and backfilling for new illumination circuits near Exit 13 on Route 8 NB