Work will continue as follows:

  • Signage continues to be posted on the jobsite.
  • Saw-cutting will begin June 10, and concrete pavement repair activities will begin June 17, from Exit 15 to 22 northbound.

Other work continuing throughout the project:

  • Illumination work on along Route 8 southbound from Exit 17 to 12

Future activities:

  • Beginning in August 2024, night work milling, surveying, and paving will begin again both north and south bound, in one-mile segments, with new pavement installed within two days.
  • This work began from the Exit 15 on-ramp and will continue northbound through Exit 22/23. Southbound work will then begin, starting from Exit 22/23 and continuing to the Exit 15 southbound off-ramp.

img 9598

img 9598

Next Post
Update for the Weeks of June 24 & July 1, 2024
Previous Post
Update for the Weeks of May 27 & June 3, 2024