Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.
Nighttime work will continue from 6PM to 6AM:
- Saw-cutting will continue, and concrete pavement repair activities will continue, northbound from Exit 15 to 22.
Daytime work will continue from 8AM to 3PM:
- Illumination work along Route 8 at Exit 14-15 area.
Future activities:
- Beginning at the end of September, night work milling, surveying, and paving will begin again, in one-mile segments, with new pavement installed within two days. Work will continue northbound to Exit 23, then southbound from Exit 23 to Exit 15.