This past week of January 29, we continued illumination work at Exits 15 – 13 southbound and on local roads, including light bases, cables and poles. Pothole repair work was also done along the entire north and southbound Route 8 corridor.

For the weeks of February 5 & 12, 2024, anticipated work is as follows:

  • We will continue illumination work on light bases, cables and poles at Exit 15 – 13 southbound and on local roads, as well continuing pothole repair work across the entire corridor north and southbound from Exits 15-22.
  • We will also begin the lining of pipes throughout the project corridor from Exits 15 to 22, both northbound and southbound.