This past week of November 27, light pole installation, light base foundation, and ramp crossing work continued along Route 8. For the next two weeks, milling and paving will also take place both during the night and during the day, as noted below.

Weeks of December 4 & 11:

  • Continued illumination work on cable and light poles on Route 8 southbound at Exit 17 and Exit 14, 8:00 AM – 3:00 PM
  • Milling of Route 8 northbound, Exit 19 – 21, and Route 8 southbound Exit 21 – 19, 8:00 PM – 5:30 AM
  • Paving Route 8 northbound from Exit 19 – 21, and Route 8 southbound the Exit 21 – 19, 9:00 AM – 3:00 PM