Nighttime work will continue from 6PM- 6AM: Saw-cutting will continue, and concrete pavement repair activities will continue, northbound from Exit 15 to 22. Daytime…
Nighttime work will continue as follows, from 6PM to 6AM: Saw-cutting and concrete pavement repair activities will continue, from Exit 15 to 22 northbound.…
Work will continue as follows: Signage continues to be posted on the jobsite. Saw-cutting will continue, and concrete pavement repair activities will continue, from…
Work will continue as follows: Signage continues to be posted on the jobsite. Saw-cutting will begin June 10, and concrete pavement repair activities will…
On May 6, 2024, the Connecticut Department of Transportation began full milling and paving operations along Route 8, as follows: Night work milling, surveying,…
Starting on Monday, May 6, 2024, the Connecticut Department of Transportation is beginning full milling and paving operations along Route 8, as follows: Night…
During the past weeks of March 18 & 25, we accomplished the following work: Illumination work, including light bases, cables, and poles, continued along…