Daytime work will continue (7AM – 3PM, Monday–Friday)

  • Both northbound and southbound traffic lanes shifted to the right shoulder to create work areas for median barrier replacement between Exits 14–15 (former Exits 18–19) and Exits 15–17 (former Exits 19–20).
  • Another work zone has been established by shifting both northbound and southbound traffic lanes to the right shoulder between Exits 14–12b (former Exits 17–16).
  • Median barrier and median drainage are underway.
    Ramp and shoulder drainage repair will continue throughout northbound and southbound from Exits 12B–18 (former Exits 15–22).

Night work will continue (6PM – 6AM, Sunday–Thursday)

  • Concrete pavement repair activities will resume northbound Exit 18 to the project limits at the North Main Street Bridge in Seymour.
  • Traffic pattern will remain the same (both directions shifted to the right shoulder).
  • Median barrier and drainage work will continue.