Please note: no work will be done over Memorial Day, from Friday, May 23 through Monday, May 26, 2025. Work will resume Tuesday, May 27, as follows:
Work will continue during the daytime, 7AM to 3PM, Tuesday through Friday (5/27—5/30) and Monday through Friday (6/2—6/6).
- Both northbound and southbound traffic lanes have moved to the right shoulder to create a work area for median barrier replacement between Exit 20 and 22 (New Exits 17-18), and to create a second work area for median barrier replacement after Exit 22 (New Exit 18).
- Median barrier and median drainage are being replaced.
- Pipe repair and lining activities will continue throughout, northbound and southbound from Exit 15 to 22 (New Exits 12B-18).
Nighttime work will continue from 6PM to 6AM, Tuesday through Thursday (5/27—5/29) and Monday through Thursday (6/2—6/5).
- Concrete pavement repair will remain paused northbound and will continue southbound at the Exit 17 southbound on-ramp.