Happy New Year!
Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.
Work will continue during the daytime, 7AM to 3PM, Monday through Friday.
- Both northbound and southbound traffic lanes have moved to the right shoulder to create work areas for median barrier replacement between Exits 14-15 (former Exits 18-19) and Exits 15-17 (former Exits 19-20). Work areas between Exits 17-18 (former Exits 20-22) and Exit 18 (former Exit 22) have been restored to their original alignment.
- Median barrier and median drainage are being replaced.
- Ramp and shoulder drainage repair will continue throughout, northbound, and southbound from Exit 12B-Exit 18 (former Exits 15-22).
Nighttime work will resume January 12 from 6PM to 6AM Sunday through Thursday nights.
- Concrete pavement repair has completed for the winter season.
- Median barrier and drainage work will continue throughout the current work zones from Exits 15-14 (former Exits 18-19).