Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.

Work will continue during the daytime, 7AM to 3PM, Monday through Friday

  • Both northbound and southbound traffic lanes have moved to the right shoulder to create a work area for median barrier replacement between Exit 20 and 22 (New Exits 17-18), and to create a second work area for median barrier replacement after Exit 22 (New Exit 18).
  • Median barrier and median drainage are being replaced.
  • Pipe repair and lining activities will continue throughout, northbound and southbound from Exit 15 to 22 (New Exits 12B-18).

Nighttime work will continue from 6PM to 6AM, Monday through Thursday

  • This work is the continuation of the concrete pavement repair activities.

NOTE: No work will be done over the holiday weekend, from Thursday April 17 through Sunday April 20. Work will resume Monday night, April 21. 