Project Plans

  1. Home
  2. Project Plans

Project Schedule

  • June 10, 2022 – Notice to Proceed
  • 2022 – Site Investigations
  • 2023 – Final Design Submittal
  • 2023 – Design Release for Construction
  • 2024 – Construction Start
  • 2029 – Anticipated Project Completion

Current Project Status

  • Completed investigations and cleaning
  • Illumination and concrete repair work
  • Final Design completed
  • Permitting completed
  • Median barrier replacement:
    • Both northbound & southbound traffic lanes have moved to the right shoulder to create work areas for median barrier replacement between Exit 15 and 17, (Former exits 19 and 20), Exit 17 and Exit 18 (former Exits 20 and 22), and Exit 18 (former Exit 22).
  • Median drainage replacement:
    • Pipe repair and lining activities will continue throughout, northbound, and southbound from Exit 12B to Exit 18 (former Exits 15 and 22).

Construction Activities

  • Work will be completed by taking lanes during off-peak hours
  • Mostly night work with some daytime activities
  • Ramp closures and detours at night
    • Anticipated two to three nights per ramp
    • Local road detours will be coordinated with Towns (detour agreements)
    • Announcements will be found on the website

Construction Staging & Phasing

  • Stage 1 – Shoulder rehabilitation
  • Stage 2 – Median Reconstruction
  • Stage 3 – Mainline pavement reconstruction
  • Center median reconstruction
  • Concrete pavement base repairs
  • Work progression South to North