Week of March 2, 2026:

  • All daytime and nighttime work will be paused during the week of March 2 due to inclement weather. Work Zones will remain in place but, no traffic patterns will be taken until 3/9/26.

Week of March 9, 2026:

As of 3/9/26, work will resume during the daytime, 7AM to 3PM, Monday through Friday.

  • Both northbound and southbound traffic lanes have moved to the right shoulder to create work areas for median barrier replacement between Exits 14-15 (former Exits 18-19) and Exits 15-17 (former Exits 19-20).
  • Median barrier and median drainage are being replaced.
  • Ramp and shoulder drainage repair will continue throughout, northbound, and southbound from Exit 12B-Exit 18 (former Exits 15-22).