Work will continue during the daytime, 7AM to 3PM, Monday through Friday

  • Both northbound and southbound traffic lanes have moved to the right shoulder to create a work area for median barrier replacement between Exit 17 and Exit 18 (former Exits 20 and 22), and to create a second work area for median barrier replacement after Exit 18 (former Exit 22).
  • Median barrier and median drainage are being replaced.
  • Pipe repair and lining activities will continue throughout, northbound, and southbound from Exit 12B to Exit 18 (former Exits 15 and 22).

Nighttime work will continue from 6PM to 6AM, alternating weekly from Monday through Thursday and Sunday through Thursday

  • Week of July 6: Nighttime work will be Monday through Thursday
  • Week of July 13: Nighttime work will be Sunday through Thursday
  • Concrete pavement repair will remain paused northbound and will continue southbound at the Exit 17 southbound on-ramp.