Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.
Work will continue during the daytime, 7AM to 3PM, Monday through Friday.
- Both northbound and southbound traffic lanes have moved to the right shoulder to create work areas for median barrier replacement between Exit 15 and 17, (Former exits 19 and 20), Exit 17 and Exit 18 (former Exits 20 and 22), and Exit 18 (former Exit 22).
- Median barrier and median drainage are being replaced.
- Pipe repair and lining activities will continue throughout, northbound, and southbound from Exit 12B to Exit 18 (former Exits 15 and 22).
Nighttime work will continue from 6PM to 6AM Sunday through Thursday nights for both weeks
- Concrete pavement repair will resume and continue northbound at the Exit 17 Northbound off-ramp